# Bank CMG - Online Banking Decon & Q2 Integration - Go Live Playbook
Source file: `Bank CMG - Online Banking Decon & Q2 Integration - Go Live Playbook - 4-13-2026.xlsx`
Analysis date: 2026-04-16
## Full analysis
I reviewed all 7 sheets in the workbook.
### 1. Workbook overview
This file is mainly a go live coordination workbook centered on the **Go Live Playbook CMG** tab. The other tabs support it with project status, Q and A, and contact lists.
The tabs are:
1. **Q2 Integration Projects**
2. **TransferNow**
3. **Go Live Playbook CMG**
4. **Bank Team Roster**
5. **Fiserv Team Roster**
6. **Q2 Main Contacts**
7. **MANTL Main Contacts**
There do not appear to be workbook formulas driving the plan. It reads like a manually maintained operating playbook.
### 2. What each sheet contains
#### Q2 Integration Projects
A simple status tracker for major integration workstreams. Most items are marked complete. Notable entries:
- mRDC and RDC marked Complete
- File Exchange marked Complete
- Integrated Teller marked Complete
- CardHub marked Complete
- Notifi marked Complete with note that SSO is confirmed
- **Communicator Open appears twice**, once Complete and once In Progress
#### TransferNow
This is a Q and A / decision log, not a task tracker. It answers operational questions about:
- whether scheduled transfers can be converted
- whether new transfers can be blocked before deconversion
- whether users will be notified about canceled future transfers
- whether Compass has an in flight transaction report
Main takeaway: the bank should expect to handle customer communication itself, and TransferNow will provide in flight transaction details on decommission day.
#### Go Live Playbook CMG
This is the main sheet and the core of the workbook. It contains the execution plan with task number, day, dates, times, owner, product, description, status, and notes.
#### Bank Team Roster
9 names with email addresses, but almost all other fields are blank.
#### Fiserv Team Roster
Most complete roster in the workbook. 11 contacts with roles, responsibilities, and emails. Only 2 have phone numbers.
#### Q2 Main Contacts
4 contacts. Only Phillip Mallory has role and responsibility populated. The other three have emails only.
#### MANTL Main Contacts
1 contact only, Aaron Landers, with email only.
### 3. Main operational picture from the playbook
The go live plan is concentrated around **April 13, 2026 through April 20, 2026**, with one follow on item on **May 17, 2026**.
The heaviest execution day is **Friday, April 17, 2026**, which has the bulk of the cutover work. The plan clusters around these areas:
#### Online Banking decommissioning
- removal of TransferNow and CashEdge access
- removal of enrollment options
- removal of bill pay access
- shutoff of retail and business online banking access
- removal of ACH Manager, Wire Manager, and Intuit/OFX access
- file cuts and delivery via MoveIT
#### Zelle cutover
- key info to Q2
- ORG ID setup
- finder and driver file exchange
- account type updates
- deployment / decoupling from RXP
- validation of retail and business Zelle
- landing page update
#### TransferNow deactivation
- scheduled SRT list
- deactivation on April 20
- confirmation email after deconversion
#### Notifi
- file handoff between Fiserv and Q2
- post conversion confirmation
- appears to stay in place via SSO rather than being removed
### 4. Biggest findings and risks
#### A. The playbook is mostly missing current status updates
Only 6 tasks have a populated status:
- 5 marked Completed
- 1 marked In Progress
- **37 task rows have blank status**
That makes the sheet weaker as a live execution dashboard because most upcoming and dependency heavy tasks are not marked ready, blocked, or complete.
#### B. There is at least one likely data entry issue
Task 9 has an invalid finish date value of **`** instead of a date. That is probably a typo and should be corrected.
#### C. Date formatting is inconsistent
Most dates are Excel serial values, but tasks 38 and 39 use literal text dates with nonbreaking spaces like **4/20/2026**. This inconsistency can cause sorting, filtering, or reporting issues.
#### D. Time zone handling is a real risk
The sheet header says **all times in Central Time**, but multiple task descriptions and notes reference **ET** deadlines. That creates room for execution mistakes during cutover, especially on April 17 and April 20.
#### E. Contact rosters are incomplete
The Bank, Q2, and MANTL contact tabs are thin:
- missing roles
- missing responsibilities
- almost no phone numbers
- no time zones
- no business units
That is a risk during incident handling or escalation.
#### F. Duplicate / ambiguous project tracking in Q2 Integration Projects
“Communicator Open – Q2 to Premier Core” appears twice with different statuses. That may reflect two phases, but as written it is ambiguous.
#### G. There are several TBD tasks close to go live
Tasks 40 to 42 for Notifi still have TBD timing. That is risky because they happen in the same window as conversion completion and cross vendor file exchange.
### 5. What looks strongest
The workbook does a good job of capturing:
- named owners for most cutover tasks
- product level segmentation
- practical task notes
- dependency style sequencing, especially around Zelle and Online Banking
- cross vendor coordination between Bank CMG, Fiserv, and Q2
The Fiserv roster is also relatively solid compared with the other roster tabs.
### 6. What looks weakest
The weakest parts are:
- incomplete live status tracking
- inconsistent data hygiene
- incomplete escalation contacts
- lack of explicit dependency fields
- no clear go or no go checkpoint section
- no contingency or rollback section on the main playbook tab
### 7. Combined assessment
This workbook is a **useful operational cutover playbook**, but it is **not yet clean enough to serve as a high confidence command center tracker** without a few fixes.
Most important actions before relying on it during execution:
1. Fix bad and inconsistent dates, especially task 9 and tasks 38 to 39.
2. Normalize all times to one standard and explicitly show CT and ET where needed.
3. Fill in statuses for all active and pending tasks.
4. Complete the Bank, Q2, and MANTL contact tabs with phone numbers, roles, and escalation paths.
5. Clarify whether the duplicate Communicator Open rows represent separate milestones.
6. Resolve the TBD timing for Notifi tasks.
Overall weighted confidence: **0.92**
The workbook is directionally strong and operationally useful, but it still has enough gaps that I would treat it as **good draft execution material, not final cutover control material**, until those fixes are made.
## Vault summary
- Main sheet is **Go Live Playbook CMG**. It is the operational cutover plan.
- Biggest risk is **execution readiness**, not missing content.
- Main issues are **blank statuses**, **incomplete contact rosters**, **inconsistent dates/times**, and **one obvious bad cell value** in task 9.
- Heaviest cutover activity is **Friday, April 17, 2026**.
- Strongest area is task level detail and ownership.
- Weakest area is real time control quality for go live.