Q2 Production Day 2 Analysis — Complete Report Index
Date: April 22, 2026
Analysis Period: Q2 Go-Live Day 1-2 (April 20-21, 2026)
Total Reports: 4 (1 general analysis + 3 detailed reports)
Overview
This collection of reports analyzes the critical issues discovered during Bank CMG's Q2 Digital Banking go-live (Day 1-2) and evaluates what the migration automation detected vs. missed.
Key Findings:
- ✅ 98.5% data quality improvement achieved (776 → 12 exceptions)
- ❌ Consumer linked accounts NOT detected (750-1,250 customers estimated backlog)
- ❌ Fraud prevention NOT included (SAC code phishing attack on Day 2)
- ❌ Operational readiness NOT assessed (no support workload projections)
Report Structure
📄 General Analysis Report
Q2 Production Analysis - Account Linking & Fraud - 2026-04-22
Contents:
- Executive summary of Day 2 production update
- What the migration automation DID well (data quality)
- What the migration automation MISSED (linked accounts, fraud prevention, support planning)
- Comparison of commercial vs. retail multi-user detection
- Cost-benefit analysis of prevention vs. reactive response
- Practical recommendations for immediate and long-term fixes
Key Quote (Mickey):
"We dumped a whole bunch of time into the treasury management business side of it and not thinking on the consumer side. And that is killing us, absolutely killing us."
Length: ~14,000 words
Audience: Management, operations team, next migration planning
Detailed Reports
📊 Report 1: Linked Account Investigation
Report 1 - Linked Account Investigation - 2026-04-22
Contents:
- Detailed profiles of 7 "MISSING_ACCOUNT" customers
- Customer ID pattern analysis (DBA identification)
- Commercial multi-user benchmark (1,337 employees, 714 clients, 1.87 avg)
- Estimated retail linked account impact (750-1,250 customers)
- Workload calculation (252-419 hours = 31-52 business days)
- Why this wasn't detected (missing Fiserv data)
- Root cause analysis (file structure is customer-centric, not account-centric)
- Cost-benefit of prevention (18-47x ROI)
Key Finding:
The 7 exceptions are the tip of the iceberg, not the full problem.
Examples:
- Steven Stenbroten (ID 1711):
steves@montfordinc.com→ Clear DBA scenario - Maureen Eckert (ID 19279):
djandme2@outlook.com→ Joint account pattern
Length: ~16,000 words
Audience: Operations team (Mickey, Carrie, Kalie, Trent), Q2 support
🚨 Report 2: Fraud Incident Timeline & Response
Report 2 - Fraud Incident Timeline & Response - 2026-04-22
Contents:
- Incident timeline (attack start → containment in ~1 hour)
- Attack pattern analysis (social engineering, go-live timing)
- What the migration automation could/couldn't do
- Response quality assessment (Grade: A- reactive, C proactive)
- Lessons learned (what worked, what to fix next time)
- Industry context (why core migrations are fraud windows)
- Recommendations for next go-live
Key Finding:
Attack timing (within 48 hours of go-live) suggests attackers had advance knowledge of migration date.
Response Summary:
- ✅ No customer losses
- ✅ Fast pattern recognition
- ✅ Multi-team coordination
- ❌ No pre-migration customer fraud warning
- ❌ No baseline metrics for anomaly detection
- ❌ No fraud monitoring dashboard
Length: ~21,000 words
Audience: Security team (Becky Jones), management, Q2 support
📈 Report 3: Post-Migration Support Dashboard Spec
Report 3 - Post-Migration Support Dashboard Spec - 2026-04-22
Contents:
- Dashboard overview (5 sections, 10+ key metrics)
- Section 1: Adoption metrics (daily logins, cumulative adoption, feature usage)
- Section 2: Technical health (failed logins, password resets, e-statements)
- Section 3: Support workload (case volume, resolution time, team capacity)
- Section 4: Security monitoring (SAC resets, failed attempts, fraud cases)
- Section 5: Open issues tracking table
- Daily reporting format (template for 8:00 AM email)
- Weekly summary format (for post-Day 14)
- Alert thresholds summary (Green/Yellow/Red for each metric)
- Implementation checklist (Week 1-4 tasks)
Key Metrics:
- Adoption: 75% by Day 14 (currently 28% on Day 2, 41% growth rate)
- Support: <20 open cases per staff (currently 150-250 per person = RED)
- Technical: <5% failed login rate
- Security: SAC reset baseline + anomaly detection
Current Status (Day 2):
- 🚨 RED Alert: Cases per staff = 150-250 (threshold: >30 = overwhelmed)
- ✅ GREEN: Adoption rate = 41% daily growth
- ⚠️ YELLOW: Fraud incident contained but monitoring ongoing
Length: ~20,000 words
Audience: Operations team, Trent (dashboard owner), management
Data Sources
Production Update (Day 2):
- Transcript of April 21, 2026 status call
- Participants: Phillip, Mickey, Carrie, Scott, Mary, Garfield
Migration Automation (q2migrationautomation folder):
mock2_fixed/migration_summary_report.txtmock2_fixed/exceptions.csv(7 MISSING_ACCOUNT customers)commercial_validation/commercial_summary_report.txtOTP4101CUSTOMER169_PARSED.xlsx(5,030 retail customers)OTP4102CLIENT169_PARSED.xlsx(714 commercial clients)OTP4102EMPLOYEE169_PARSED.xlsx(1,337 commercial employees)OTP4102ACCTGROUP169_PARSED.xlsx(794 account groups)
Key Statistics
Migration Automation Success Metrics
| Metric | Mock 1 | Mock 2 | Improvement |
|---|---|---|---|
| Duplicate Logins | 26 | 0 | +100.0% |
| Transfer Errors | 243 | 0 | +100.0% |
| Missing Accounts | 406 | 7 | +98.3% |
| Template Errors | 101 | 0 | +100.0% |
| Missing Addresses | 18 | 0 | +100.0% |
| Total Exceptions | 776 | 12 | +98.5% |
Production Reality (Day 2)
| Issue | Impact | Status |
|---|---|---|
| Linked account backlog | 750-1,250 customers, 252-419 hours work | 🚨 In progress, team overwhelmed |
| SAC code phishing | High-volume attack, 0 confirmed losses | ✅ Contained in 1 hour |
| E-statements | Some customers can't view | ⚠️ Fix ready for testing |
| Account nicknames | Not migrated for retail | ⚠️ Brian working on it |
| Notify/Fiserv messages | Final migration incomplete | ⚠️ With both vendors |
The Gap: Data Quality ≠ Operational Readiness
What Was Validated ✅
- Customer records are complete (name, email, address)
- No duplicate logins
- Accounts are linked to correct customers
- Templates and transfers migrated successfully
What Was NOT Validated ❌
- How many customers need manual account linking post-migration?
- How long will each account link take to set up?
- What's the expected support call volume?
- What fraud risks exist during the go-live window?
- What metrics should be tracked post-migration?
The automation answered: "Can we migrate the data?"
It did NOT answer: "What happens after we migrate?"
Recommendations Summary
Immediate (Next 48 Hours)
- Quantify linked account backlog — Query Q2 for open cases, calculate remaining hours
- Set up fraud monitoring dashboard — SAC resets, failed logins, anomaly detection
- Document account linking runbook — Step-by-step Q2 workflow, required data, time estimates
- Create daily dashboard — Start sending 8:00 AM status email to team
Short-Term (Next 2 Weeks)
- Request missing Fiserv data — Joint account table, authorized signer list, DBA cross-reference
- Build proactive customer outreach — Email customers BEFORE they call ("We're setting up your access")
- Track metrics daily — Cases added, time per case, backlog remaining, completion ETA
- Enhance exception reporting — Add "Linked Account Risk" field, flag possible authorized users
Long-Term (Next Migration)
- Add linked account detection to automation — Cross-reference customer login table with account ownership
- Create pre-migration linked account report — Estimate impact, plan remediation, set expectations
- Build fraud risk assessment — High-risk accounts, baseline metrics, customer education plan
- Define operational readiness criteria — Support workload projections, dashboard specs, playbooks
Cost-Benefit Analysis
Cost of Reactive Response (Actual)
- Linked accounts: 252-419 hours manual work (31-52 business days, 1 FTE)
- Fraud incident: 24 person-hours response + monitoring
- Customer support calls: 188-417 hours (diagnosing linked account issues)
- Total: 440-756 hours = 11-18 weeks of 1 FTE
Cost of Proactive Prevention (Hypothetical)
- Request Fiserv linked account data: 1 day
- Parse and validate linked accounts: 1 day automation development
- Generate linked account migration plan: 1 hour
- Send fraud warning email to customers: 1 hour
- Build fraud monitoring dashboard: 6 hours
- Total: 16-24 hours
ROI of Prevention
440-756 hours saved ÷ 16-24 hours spent = 18-47x return
(Not including customer trust impact, which is harder to quantify but significant)
Lessons Learned
What the Automation Did Well
✅ Data quality validation — 98.5% exception reduction is real and valuable
✅ Commercial multi-user detection — Validated 1,337 employees across 714 clients
✅ Fast processing — <1 minute for retail, <5 minutes for commercial
✅ Mock 1 comparison — Showed clear improvement over baseline
What the Automation Missed
❌ Retail linked account detection — No equivalent of commercial employee files
❌ Operational impact estimation — No support workload projections
❌ Fraud risk assessment — No security baseline or monitoring plan
❌ Post-migration playbook — No guidance for common support issues
Root Cause
Scope Definition:
The automation was scoped for "data validation" not "operational readiness."
Assumption:
Clean data = smooth go-live (proven false by production reality)
Data Gap:
Fiserv retail extract does not include linked account relationships (or they weren't requested)
Next Actions
For Operations Team (Mickey, Carrie, Kalie, Trent)
- Read Report 1 (Linked Account Investigation) — Understand the 750-1,250 backlog
- Implement Report 3 (Dashboard Spec) — Start tracking metrics daily
- Use linked account runbook to document current workflow (capture actual time per case)
For Security Team (Becky Jones)
- Read Report 2 (Fraud Incident) — Review response quality assessment
- Set up fraud monitoring dashboard (SAC resets, failed logins)
- Calculate baseline metrics from Q2 production data
For Management
- Read General Analysis — Understand gap between data quality and operational readiness
- Review cost-benefit analysis (18-47x ROI for prevention)
- Approve additional temporary support staff if cases per person >30 (currently 150-250)
For Next Migration Planning
- All reports → Document lessons learned
- Add linked account detection to automation roadmap
- Add fraud risk assessment to automation roadmap
- Add operational readiness criteria to migration checklist
File Locations
Obsidian Vault:
CMG Project/Q2 Production Analysis - Account Linking & Fraud - 2026-04-22.mdCMG Project/Report 1 - Linked Account Investigation - 2026-04-22.mdCMG Project/Report 2 - Fraud Incident Timeline & Response - 2026-04-22.mdCMG Project/Report 3 - Post-Migration Support Dashboard Spec - 2026-04-22.mdCMG Project/Q2 Production Issues - Complete Analysis Index - 2026-04-22.md(this file)
Local Project:
C:\Users\garfield.heron\IdeaProjects\AIO\q2migrationautomation\(automation code and data)C:\Users\garfield.heron\IdeaProjects\AIO\q2migrationautomation\mock2_fixed\(Mock 2 results)C:\Users\garfield.heron\IdeaProjects\AIO\q2migrationautomation\commercial_validation\(Commercial results)
Total Word Count
- General Analysis: ~14,000 words
- Report 1 (Linked Accounts): ~16,000 words
- Report 2 (Fraud Incident): ~21,000 words
- Report 3 (Dashboard Spec): ~20,000 words
- Total: ~71,000 words
Conclusion
The Q2 migration automation was highly successful at data validation (98.5% exception reduction) but had zero coverage of operational readiness (linked accounts, fraud prevention, support planning).
Mickey's feedback is the key insight:
"We dumped a whole bunch of time into the treasury management business side of it and not thinking on the consumer side."
The automation followed the same pattern: Deep commercial analysis, shallow retail analysis.
The result: 750-1,250 customers requiring manual account linking (252-419 hours of work), which is "absolutely killing us."
This was preventable. The data exists in Fiserv core, but it wasn't requested or validated.
The lesson: Migrating data successfully ≠ Operating successfully post-migration.
Tags: #bank-cmg #q2-migration #production-issues #lessons-learned #linked-accounts #fraud #operational-readiness
Date: April 22, 2026
Author: Garfield Heron
Status: ✅ Complete Analysis